21 June 2018

AEMC proposes changes for generators seeking to connect to the national electricity grid

The AEMC is currently considering implementing a rule change that proposes "a flexible approach to setting standards that enables targeted, least-cost ways of connecting new generators". The rule change amends:

  • the negotiation process for generators wishing to connect to the transmission network; and
  • the technical requirements for connecting generators to the transmission network.

The AEMC have set up a web page which provides additional information as well as downloadable copies of the AEMC information Sheet and the draft AEMC determination.

Summary of proposed amendment

The proposed amendments to the National Electricity Rules are primarily aimed at addressing the changing energy mix as the number of asynchronous generators (ie wind/solar) grows and distributed generation increases, with the overall goal of ensuring that the power system remains in a secure state.

The rule change modifies the existing rules in two ways:

  • it streamlines the connection negotiation process by clarifying the requirements that applicants must comply with and the information that they must provide when proposing negotiated access standards; and
  • it imposes more strenuous technical requirements on generators through the imposition of higher access standards.

Connection negotiation process

Once the rule commences, applicants will be required to propose a level of performance that is as close as practicable to the automatic access standard, having regard to a limited set of criteria (eg the need to protect the plant from damage and the commercial and technical feasibility of doing so).

Applicants will also be required to provide the network service provider and AEMO with reasons and evidence as to why the proposed negotiated access standard is appropriate.

Change to performance standards

The draft determination also proposed a number of changes to the technical requirements under the automatic and minimum access standards that generators need to meet in order to have their connection agreement authorised by AEMO.

These technical requirements generally relate to a generation plant’s ability to:

  • control their active power output and limit their contribution to frequency and voltage disturbances;
  • supply and absorb reactive power where this service is needed;
  • inject and absorb reactive current during disturbances; and
  • maintain operation in the face of certain frequency and voltage disturbances.

These proposed amendments to the technical requirements may increase the capex costs of a generator project and/or lead to delays in project development as projects assess whether they can meet the automatic access standard, and then provide evidence as to why this standard cannot be met by the generator.

Transitional arrangements

Transitional arrangements have been proposed for:

  • existing connection enquiries;
  • existing applications to connect;
  • existing offers to connect; and
  • existing connection agreements.

These transitional arrangements are quite detailed and nuanced in their application, and we think that parties seeking to rely on these transitional provisions will need to work very carefully thought the Rules to ensure that they meet the criteria before seeking to rely on them.

We expect that the regulators will also be seeking to do the same to ensure that the performance of the system is not impacted by grandfathered connections.

Next steps

The AEMC is currently accepting stakeholder submissions in response to the draft rule determination until 13 July 2018, with the changes currently scheduled to take effect from 2 October 2018.

Share on LinkedIn Share on Facebook Share on Twitter
    You might also be interested in

    Very shortly, the U.S.-based Alternative Reference Rates Committee (ARRC) will make its much-anticipated formal recommendation of forward-looking term Secured Overnight Financing Rates (Term SOFR)...

    27 July 2021

    The NSW Government has announced tighter restrictions to the construction sector in the Public Health (COVID-19 Temporary Movement and Gathering Restrictions) Amendment (No 8) Order 2021 made under...

    19 July 2021

    Major infrastructure projects procured by Federal and State governments are fuelling continued Australian growth and the pipeline of future projects continues to be strong.

    12 July 2021

    On 8 July 2021, the Governor in Council made the Building Industry Fairness (Security of Payment) and Other Legislation Amendment (Postponement) Regulation 2021 (“Postponement Regulation”) postponing...

    09 July 2021

    This site uses cookies to enhance your experience and to help us improve the site. Please see our Privacy Policy for further information. If you continue without changing your settings, we will assume that you are happy to receive these cookies. You can change your cookie settings at any time.

    For more information on which cookies we use then please refer to our Cookie Policy.